Estimating, Costing And Supervision | Question Paper | 2075 [2019] | RE-CIE701 | SEE | DOWNLOAD
SEE estimating costing and supervision question paper 2075-2019 re-cie701
DR Gurung
| DOWNLOAD PDF | SEE Estimating, Costing And Supervision | Question Paper | RE-CIE701 | 2075/2019Also Check:
Check and Download | All Question Papers Of SEE | 2075/2019
Check and Download | All Question Papers Of SEE | 2074/2018
Candidates are required to give their answer according to the given instructions.
Group 'A'
Attempt any ten questions. [10x1=10]1. What is the unit of measurement of brickwork?
2. Write the formula to calculate area section of regular triangular trench.
3. Write the full form of PCC.
4. Estimate the sectional area of regular circular trench with radius 7m.
5. What is the density of steel?
6. Define punning.
7. Why BPT is necessary in water supply system?
8. What is the standard size of C6I sheet?
9. What do you mean by rate analysis?
10. What do you mean by Tender Notice?
11. List any one duty of supervisor.
12. What do you mean by Measurement Book?
13. What do you mean by Bill of Quantity?
2075/2019 SEE Question Paper., Download SEE Question Paper 2075/2019., SEE Secondary Education Examination Nepal., SEE Question Papers and Solution 2075/2019., Solution Of Question SEE 2075/2019., SEE Estimating, Costing and Supervision re-cie701 Question 2075-2019., Estimating, Costing and Supervision re-cie701 Question Paper 2075/2019., SEE Estimating, Costing and Supervision re-cie701 Question Paper 2075/2019., SEE Solved Exam Paper Of Estimating, Costing and Supervision re-cie701 2075-2019., Download Question Paper Of Estimating, Costing and Supervision re-cie701 2075-2019., Check SEE Estimating, Costing and Supervision re-cie701 Question Paper 2075/2019., Solution Of Estimating, Costing and Supervision re-cie701 Question SEE 2075/2019., Check and Download PDF Estimating, Costing and Supervision re-cie701 Question 2075/2019., SEE 2075-2019 Estimating, Costing and Supervision re-cie701., Question Paper of all Provinces 2075/2019 Estimating, Costing and Supervision re-cie701., Question With Solution Secondary Education Examination SEE. alert-info
2. Write the formula to calculate area section of regular triangular trench.
3. Write the full form of PCC.
4. Estimate the sectional area of regular circular trench with radius 7m.
5. What is the density of steel?
6. Define punning.
7. Why BPT is necessary in water supply system?
8. What is the standard size of C6I sheet?
9. What do you mean by rate analysis?
10. What do you mean by Tender Notice?
11. List any one duty of supervisor.
12. What do you mean by Measurement Book?
13. What do you mean by Bill of Quantity?
Group 'B'
Attempt any five questions. [5x2=10]
14. Convert 12 ft. into meters.
15. Define the following terms.
(i) Hooks (ii) Development length
16. List any two specifications of plastering.
17. What are the contents to be covered in site order book?
18. Write any two uses of log book.
19. The length of a room is 5.5m and its height 2m. If the rate of plastering is Rs. 50 per m2, then what will be the total cost?
20. Write short note on site safety.
15. Define the following terms.
(i) Hooks (ii) Development length
16. List any two specifications of plastering.
17. What are the contents to be covered in site order book?
18. Write any two uses of log book.
19. The length of a room is 5.5m and its height 2m. If the rate of plastering is Rs. 50 per m2, then what will be the total cost?
20. Write short note on site safety.
Group 'C'
Attempt any five questions. [5x4=20]
21. Discuss the relationship between client, contractor and consultant.
22. Explain the layout work of building.
23. List any four components of construction site management. Explain any three of them.
24. Calculate the quantity of materials required for preparing 1m3 of RCC works for 1:2:4 cement concrete. Also prepare the analysis of rates for materials only. (Assume suitable data as required.)
25. Calculate the quantity of earthwork in excavation and fill it up in the measurement based on given drawing.
26. Explain about any two types of estimate in brief.
Check SEE Estimating, Costing and Supervision Question paper of 2075-2019 re-cie701.
22. Explain the layout work of building.
23. List any four components of construction site management. Explain any three of them.
24. Calculate the quantity of materials required for preparing 1m3 of RCC works for 1:2:4 cement concrete. Also prepare the analysis of rates for materials only. (Assume suitable data as required.)
25. Calculate the quantity of earthwork in excavation and fill it up in the measurement based on given drawing.
26. Explain about any two types of estimate in brief.
Check SEE Estimating, Costing and Supervision Question paper of 2075-2019 re-cie701.
DR Gurung
A Learner
(अज्ञान जस्तो ठूलो शत्रु अरु केही छैन।) 🙏🙏
Suggestions and/or questions are always welcome, either post them in the comment form or send me an email at drgurung82@gmail.com.
However, comments are always reviewed and it may take some time to appear. Always keep in mind "URL without nofollow tag" will consider as a spam.
To add an image:
[image] image_url [/image]
To add a code block:
[code] your_code [/code]
To add a quote:
[quote] your_quote [/quote]
To add a link:
[link] your_link_text | link_url [/link]